Transportation and delivery

How is the labeling of units worked out?

Each bathroom pod is labeled with a unique serial number, for traceability within construction process.

What's the procedure to notify any deviation from the ordered equipment module current content or other deviations from the factory to the project?

We communicate to the customer, before the delivery, any deviation from the project occurred for any reason so that he can make prompt decisions.

What is the weight of a Bathroom Pod?

The weight of a Bathroom Pod depends on its dimension and on the technology selected (concrete - CBM or metal frame - CBL). On the floor surface the weight of a lightweight bathroom pod is between 200 and 300 kg/m² (overall weight usually between 1 to 3 tons). For those with a concrete monolithic structure is between 500 and 700 kg/m ² (overall weight usually between 2 to...

Since the order, what is the delivery time for a Bathroom Pods?

Start time delivery is normally about 17 weeks from the order and the consequent approval of the executive design (5 weeks for the realization and approval of the sample and 12 weeks for the production and the beginning of deliveries which will then be carried on according to the needs of the construction site). In case of production without the approval of the sample, deliveries will start normally after 14 weeks from the order and acceptance of the final project.

 

Will the delivery note shall contain the date when the module has been completed?

Delivery notes normally show the serial number of each unit and also show the date of its completion.